PMI-PBA Dumps PDF, Business Analysis Dumps, download Business Analysis free Dumps, PMI Business Analysis exam questions, free online Business Analysis exam questionsYou have to pass the PMI-PBA exam to receive the certification from PMI. To increase the effectiveness of your study and make you familiar with the actual exam pattern, we have prepared this PMI Business Analysis sample questions. Our Sample PMI Professional in Business Analysis Practice Exam will give you more insight about both the type and the difficulty level of the questions on the PMI Business Analysis exam.

However, we are strongly recommending practice with our Premium PMI Professional in Business Analysis (PMI-PBA) Practice Exam to achieve the best score in your actual PMI-PBA Exam. The premium practice exam questions are more comprehensive, exam oriented, scenario-based and exact match of PMI Professional in Business Analysis exam questions.

PMI Business Analysis Sample Questions:

01. A business analyst has been assigned to a project team that is redesigning the company’s website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.
Which type of requirements are these?
a) Tested
b) Out-of-scope
c) Implemented
d) In-scope
 
02. A business analyst has started a project for a system enhancement. In order to determine how the requirements will be approved, the business analyst schedules a meeting with the stakeholders to discuss the proposed approval process.
Which measure of effective decision making allows the business analyst to finalize the process for requirement approval?
a) The requirements approval process is documented.
b) The requirements verification process is documented.
c) The requirements validation process is documented.
d) The requirements elicitation process is documented.
 
03. A business analyst is assigned to a business process re-engineering project. In addition to planning a workshop to elicit requirements, the business analyst wants to send out a survey to gather data to use in a statistical analysis on user satisfaction with the current business process.
Which of the following types of surveys would be most appropriate to create and why?
a) An open-ended survey to allow users the opportunity to explain their opinions on the current business process
b) An open-ended survey to collect different opinions on the current business process
c) A closed-ended survey using the Likert scale to rank specific areas of the current business process
d) A closed-ended survey to pose several multiple choice questions and ask the users if the current business process is correct
 
04. A company has completed a major project within time, cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment.
From the business analysis perspective, the main reason for this business failure was a failure to:
a) set the product positioning.
b) gather the appropriate usability requirements.
c) review and evaluate market expectations.
d) establish measurable success criteria in the business case.
 
05. A company is awarded a contract to design and build a custom product. The contract references a detailed technical specification.
What is the best action to take to ensure the design meets customer requirements?
a) Create a system requirements verification matrix to trace the design to the technical requirements and include verification methods.
b) Generate a design package for the product and ask the customer to verify that the design meets his or her technical needs.
c) Conduct a one-on-one interview with each member of the technical team to ensure that they understand the customer’s specification.
d) Develop a test plan to verify that the product meets the performance requirements in the technical specification.
 
06. A company is developing a new product for a customer and is required to verify and validate the product against the customer’s acceptance test plan and requirements. The product was successfully verified against the acceptance test criteria, but the customer does not believe that the product meets the requirements.
This occurred because the customer’s acceptance test plan:
a) was incomplete and missing requirements.
b) was not included in the work breakdown structure.
c) was not formally accepted by the company.
d) did not have measurable and testable requirements.
 
07. A company is working on the next big release of their best-selling product. The requirements will be validated through in-person validation sessions.
What would be the most viable technique to use in this scenario?
a) A use-case development session
b) A brainstorming session
c) A review of the solution prototype
d) A review of the previous version
 
08. A company wants to improve the service to its customers by reducing complaint response time by 40%. To achieve this goal, it is necessary to redesign and optimize their internal processes and support it with a new product. The client thinks that disruption and short-term loss of productivity is inevitable.
Where can the business analyst best reflect the intangible costs associated with this change?
a) In the requirements specification document
b) In the balanced score card chart
c) In the pay-back analysis
d) In the business case
 
09. A new project is in the planning phase.
What should the business analyst consider with regard to planning the requirements change process?
a) How requirement changes will be implemented
b) How requirement changes will be communicated
c) How requirement changes will impact the requirements baseline
d) How requirement changes will impact the validation plan
 
10. After several meetings with different groups of users, a business analyst has gathered the requirements for a large IT project. Now, the business analyst needs to document those requirements in a way that is clearly understood by the development team and provides enough information to check if the requirement has been met.
Which of the following would work best in this case?
a) User stories
b) Flow chart
c) Prototyping
d) Functional specifications

Answers:

Question: 01
Answer: b
Question: 02
Answer: a
Question: 03
Answer: c
Question: 04
Answer: d
Question: 05
Answer: a
Question: 06
Answer: d
Question: 07
Answer: c
Question: 08
Answer: d
Question: 09
Answer: c
Question: 10
Answer: d