PMI PMP Certification Exam Sample Questions

PMP Dumps PDF, Project Management Dumps, download Project Management free Dumps, PMI Project Management exam questions, free online Project Management exam questionsYou have to pass the PMP exam to receive the certification from PMI. To increase the effectiveness of your study and make you familiar with the actual exam pattern, we have prepared this PMI Project Management sample questions. Our Sample PMI Project Management Professional Practice Exam will give you more insight about both the type and the difficulty level of the questions on the PMI Project Management exam.

However, we are strongly recommending practice with our Premium PMI Project Management Professional (PMP) Practice Exam to achieve the best score in your actual PMI PMP Exam. The premium practice exam questions are more comprehensive, exam oriented, scenario-based and exact match of PMI Project Management Professional exam questions.

PMI Project Management Sample Questions:

01. What are the inputs to the Develop Project Charter process?
a) Agreements, business documents, EEFs, and OPAs
b) Business case, benefits management plan, and OPAs
c) Agreements, EEFs, and OPAs
d) Business case, benefits management plan, EEFs
 
02. You are performing the Manage Quality process and establishing expected values for the dependent relationships in the hierarchy. Which technique are you using?
a) Affinity diagrams
b) PDPC
c) Tree diagrams
d) Interrelationship digraphs
 
3) You are the project manager for the JHN Project. Mike, a project manager you are mentoring, does not know which plan he should reference for guarding the project scope. Which plan does Mike need?
a) The scope charter
b) The scope validation
c) The scope management plan
d) The scope change control system
 
04. Why should a project team complete lessons learned documentation?
a) To ensure project closure
b) To show management what they’ve accomplished in the project
c) To show the project stakeholders what they’ve accomplished in the project
d) To help future project teams complete their projects more efficiently
 
05. If your expected value is 110 and the standard deviation is 12, which of the following is true?
a) There is approximately a 99 percent chance of completing this activity in 86 to 134 days.
b) There is approximately a 68 percent chance of completing this activity in 98 to 122 days.
c) There is approximately a 95 percent chance of completing this activity in 98 to 122 days.
d) There is approximately a 75 percent chance of completing this activity in 86 to 134 days.
 
06. You need to communicate information in a multidirectional fashion with several stakeholders. Which of the following is true?
a) This describes push communication, which is a communication model.
b) This describes interactive communication, which is a communication method.
c) This describes communication requirements analysis, which is a communication model.
d) This describes pull communication, which is a communication method.
 
07. Which of the following best characterizes Six Sigma?
a) Stipulates that quality must be managed in
b) Asserts that quality must be a continuous way of doing business
c) Focuses on improving the quality of the people first, then improving the quality of the process or project
d) Focuses on process improvement and variation reduction by using a measurement-based strategy
 
08. The amount of authority a project manager possesses can be related to all of the following except which one?
a) The organizational structure
b) The interaction with various levels of management
c) The key stakeholder’s influence on the project
d) The project management maturity level of the organization
 
09. A negative result from an SV calculation means which of the following?
a) PV is higher than EV.
b) PV equals 1.
c) EV is higher than PV.
d) EV is higher than AC.
 
10. Once you earn the PMP, the certification is valid for how long?
a) One year
b) Five years
c) Forever
d) Three years

Answers:

Question: 01
Answer: a
Question: 02
Answer: c
Question: 03
Answer: c
Question: 04
Answer: d
Question: 05
Answer: b
Question: 06
Answer: b
Question: 07
Answer: d
Question: 08
Answer: c
Question: 09
Answer: a
Question: 10
Answer: d

If you find any errors or typos in PMI Project Management Professional (PMP) sample question-answers or online PMI Project Management practice exam, please report them to us on feedback@processexam.com

Your rating: None Rating: 4.9 / 5 (74 votes)