PeopleCert PRINCE2 Practitioner Certification Exam Sample Questions

PRINCE2 Practitioner Dumps PDF, PRINCE2 Project Management Dumps, download PRINCE2 7 Practitioner free Dumps, PeopleCert PRINCE2 Project Management exam questions, free online PRINCE2 7 Practitioner exam questionsYou have to pass the PRINCE2 Practitioner exam to receive the certification from PeopleCert. To increase the effectiveness of your study and make you familiar with the actual exam pattern, we have prepared this PeopleCert PRINCE2 Project Management sample questions. Our Sample PeopleCert PRINCE2 Project Management Practitioner (Version 7) Practice Exam will give you more insight about both the type and the difficulty level of the questions on the PeopleCert PRINCE2 7 Practitioner exam.

However, we are strongly recommending practice with our Premium PeopleCert certified PRINCE2 Project Management Practitioner (Version 7) Practice Exam to achieve the best score in your actual PeopleCert PRINCE2 Practitioner Exam. The premium practice exam questions are more comprehensive, exam oriented, scenario-based and exact match of PeopleCert PRINCE2 Project Management Practitioner (Version 7) exam questions.

PeopleCert PRINCE2 Project Management Sample Questions:

01. Reference Scenario: click here
Additional Information: click here
During stage 4, the restaurant staff request an additional storage unit for the restaurant, which will involve amending the 'restaurant designs'. Although it was not originally specified, the staff feel the unit is important because the restaurant would otherwise have insufficient storage capacity.
Which role should carry out the following action in response to this request for change: decide whether adding the storage unit would reduce restaurant seating capacity and so affect achievement of the predicted increase in restaurant revenue?
a) Senior Supplier
b) Senior User
c) Project Manager
d) Team Manager
e) Project Support
 
02. Additional Information: click here
Because of his ability to make key decisions and commit major resources, the Director from GDC has been appointed to the project board as a senior user.
Is this an appropriate application of the organizing practice, and why?
a) Yes, because the interests of those who will be designing and developing the landscaping products need to be represented by the project board.
b) Yes, because the GDC Director will be in a position to make decisions on issues which could impact the integrity of the overall solution.
c) No, because the GDC Director is from a commercially separate company, and commercially separate suppliers should not take a position on the project board.
d) No, because the GDC Director should not be committing to user resources, or monitoring products against user requirements.
 
03. During stage 4, an issue was raised by an ABC trainer that the 'classroom-based training materials' contained errors, even though they were signed off during stage 3. They had been based on materials from a previous course and still contained references to that course. The impact of this issue is now being assessed.
As part of the controlling a stage process, the project manager updates the issue register to show that the materials cannot be finalized within the time tolerance for stage 4.
During which controlling a stage activity should this action happen?
a) Review work package status
b) Escalate issues and risks
c) Capture and examine issues and risks
d) Authorize a work package
 
04. Additional Information: click here
Which individual would be most appropriate for the senior user role on the Woodglen Hotel refurbishment project?
a) GDC's Project Manager
b) WLG's CEO
c) Operations Director
d) Woodglen Hotel General Manager
 
05. The Calendar project was delivered as originally planned and is now preparing for planned closure. Stage 3 is its final management stage.
Which statement about the closure of this project is correct?
a) Whether the calendar achieves its objective of countering the decline in orders will be confirmed in the closing a project process, because the benefits management approach is created in that process.
b) A formal quality review meeting, chaired by the project manager, should be held for the project board to compare the final deliverable against the project product description, because the closing a project process uses the project product description to verify what was delivered.
c) The stage plan for stage 3 should contain details of the products to be created or updated during the closing a project process, because closure activities are planned as part of the stage plan for the final stage.
d) At the end of stage 3, the managing a stage boundary process should be used to update the project plan with actuals from the final stage, because an objective of that process is to review and, if necessary, update the project initiation documentation.
 
06. Consider the following planning steps:
Creating product descriptions
Identifying activities
Creating a product hierarchy
Creating a product sequence
Which of these steps are part of product-based planning?
a) 1, 2, 3
b) 2, 3, 4
c) 1, 2, 4
d) 1, 3, 4
 
07. Which management product defines the detailed nature, purpose and function of a product?
a) Product description
b) Quality register
c) Project product description
d) Plan
 
08. In the controlling a stage process, which activity is used to update the stage plan with actuals?
a) Review work package status
b) Report highlights
c) Take corrective action
d) Review the stage status
 
09. Which of the following is NOT an action carried out when preparing for planned closure?
a) Update the project plan with actuals from the final stage
b) Update the project management team structure for the next stage
c) Check the status of all the project's products to confirm that each has been approved
d) Confirm that the project has delivered what is defined in the project product description
 
10. Reference Scenario: click here
Additional Information: click here
‘Interior design models’ are being created during stage 2. These will be put on display for the hotel’s staff and guests to view and provide feedback.
Feedback from the staff and guests will then be used to further design and improve the ‘refurbished hotel’. The Interior Designer has asked the hotel’s General Manager to review the ‘interior design models’ before they are put on display. This approach has been planned and documented as part of the quality management approach.
Why is documenting this in the quality management approach an appropriate action?
a) Because the quality management approach should describe the quality control methods to be used, such as reviews and gathering user feedback, and when they will be applied.
b) Because the quality that the General Manager expects from the ‘interior design models’ needs to be agreed and documented.
c) Because the acceptance criteria for the ‘refurbished hotel’ must be recorded in the quality management approach.
d) Because the quality management approach is used to summarize all the quality activities that have been planned or have taken place.

Answers:

Question: 01
Answer: b
Question: 02
Answer: d
Question: 03
Answer: c
Question: 04
Answer: d
Question: 05
Answer: c
Question: 06
Answer: d
Question: 07
Answer: a
Question: 08
Answer: d
Question: 09
Answer: b
Question: 10
Answer: a

If you find any errors or typos in PeopleCert certified PRINCE2 Project Management Practitioner (Version 7) (PRINCE2 Practitioner) sample question-answers or online PeopleCert PRINCE2 7 Practitioner practice exam, please report them to us on feedback@processexam.com

Your rating: None Rating: 4.9 / 5 (114 votes)